Wolf Bog Wind Farm (8.8 MW)
Wolf Bog Wind Farm is an 8.8 MW wind farm project in Mid and East Antrim, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 November 2007; the record was last updated on 23 February 2010.
8.8 MWwind farm
operationalstatus in REPD
23 February 2010record last updated
Mid and East Antrimcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 1 May 2004 | Application submitted |
| 2 November 2005 | Planning permission granted |
| 1 November 2007 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 8.8 MW
- Status (REPD)
- operational
- Record last updated
- 23 February 2010
- Operator or applicant
- B9 Energy / RES
- Planning authority
- Mid and East Antrim
- Planning application reference
- G/2004/1532/F
- Turbines
- 5
- Address (REPD)
- Wolf Bog, Tildarg, nr Ballyclare, Co. Antrim
- Council area (by location)
- Mid and East Antrim
- Time to decision
- 79 weeks
- REPD reference
- 3242
Who decides
| Applications | Mid and East Antrim | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 30 | 10,236 |
| Refused | 5 (17%) | 19% |
| Solar refused | 0 of 6 | 12% |
| Onshore wind refused | 5 of 22 | 45% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 45.2 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Whappstown & Castlegore Windfarms | wind farm | 23.1 | approved, not built | 2.6 |
| Drumadarragh Wind Farm | wind farm | 8 | refused on appeal | 3.1 |
| Kells Solar Farm | solar farm | 50 | application submitted | 4.3 |
| Douglas Top | wind farm | 51 | application withdrawn | 5.2 |
| Battery Energy Storage System Development in Ballymena | battery storage | 79 | approved, not built | 5.2 |
| Cloghinarney | wind farm | 13.8 | refused on appeal | 5.8 |
| Corby Knowe | wind farm | 5 | operational | 6.4 |
| Carncome, Lislunnan Road | battery storage | 150 | approved, not built | 6.4 |
| Elliot's Hill Wind Farm | wind farm | 5 | operational | 7.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8043, -6.0806).