Energy Projects Near You

Millar Farm (6 MW solar farm)

Millar Farm is a 6 MW solar farm project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 March 2017; the record was last updated on 4 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWsolar farm
operationalstatus in REPD
4 April 2017record last updated
Antrim and Newtownabbeycouncil area

Planning timeline

DateStage
3 March 2015Application submitted
22 July 2015Planning permission granted
28 November 2016Construction started
27 March 2017Operational

Project details

Technology
solar farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
4 April 2017
Operator or applicant
Lightsource Renewable Energy
Planning authority
Antrim and Newtownabbey
Planning application reference
T/2015/0094/F
Address (REPD)
Lands 90m west of lands to the South of 72 Milltown Road
Council area (by location)
Antrim and Newtownabbey
Time to decision
20 weeks
REPD reference
5085

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
Steeple Roadsolar farm25approved, not built2.0
South Antrim Solar Park - Phase 2solar farm39.5approved, not built5.3
South Antrim Solar Park - Phase 1solar farm6.5operational5.3
Battery Energy Storage System Facility in Antrimbattery storage50approved, not built6.5
Corby Knowewind farm5operational6.7
Carncome, Lislunnan Roadbattery storage150approved, not built7.0
Elliot's Hill Wind Farmwind farm5operational7.7
Battery Energy Storage System Development in Ballymenabattery storage79approved, not built8.2
Kells Solar Farmsolar farm50application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7415, -6.2388).