Energy Projects Near You

Battery Energy Storage System Facility in Antrim (50 MW)

Battery Energy Storage System Facility in Antrim is a 50 MW battery storage project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 March 2025, not yet built; the record was last updated on 1 April 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
1 April 2025record last updated
Antrim and Newtownabbeycouncil area

Planning timeline

DateStage
16 May 2024Application submitted
21 March 2025Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
1 April 2025
Operator or applicant
Heron Storage Limited
Planning authority
Antrim and Newtownabbey
Planning application reference
LA03/2024/0351/F
Address (REPD)
Lands Approximately 550m S. of 99 Dublin Rd. and , 650m W. of 120 Dublin Road, Antrim
Council area (by location)
Antrim and Newtownabbey
Time to decision
44 weeks
REPD reference
16592

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
South Antrim Solar Park - Phase 1solar farm6.5operational1.4
South Antrim Solar Park - Phase 2solar farm39.5approved, not built1.4
South of Ballyscultysolar farm6.2refused on appeal5.5
Millar Farmsolar farm6operational6.5
Steeple Roadsolar farm25approved, not built7.2
Seegronan Wind Farm Extensionwind farm9approved, not built7.4
Seegronanwind farm13.8operational7.4
Moira Roadsolar farm6.5operational8.7
Lands West of Belfast Roadsolar farm10operational8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6834, -6.2241).