Energy Projects Near You

Solar, wind and battery projects near Larne (BT40)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT40 (Mid and East Antrim): 2 are waiting for a planning decision, 3 approved but not yet running. The largest live scheme is Power Generation Development in Islandmagee (100 MW battery storage, application submitted on 27 June 2023, no decision recorded; REPD status may be out of date), 4.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
2awaiting a decision
3approved, not running
0operational

Projects within 10 km of BT40

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ballykeel Wind Farmwind farmwind farm16.1approved, not built may be out of dateupdated Sep 2018Dec 2013granted Dec 2016Sep 2018Mid and East Antrim0.6
Quarterland Road, Islandmageebattery storagebattery storage75approved, not builtupdated Jan 2024Mar 2023granted Jan 2024Jan 2024Mid and East Antrim3.0
Mullaghsandall Road wind farmwind farmwind farm10refused on appealupdated May 2016Apr 2013refused Jul 2014May 2016Mid and East Antrim4.2
Power Generation Development in Islandmageebattery storagebattery storage100application submitted may be out of dateupdated Dec 2025Jun 2023—Dec 2025Mid and East Antrim4.2
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Larne Roadwind turbinewind turbine0.3approved, not built may be out of dateupdated Feb 2021Nov 2019granted Jan 2021Feb 2021Mid and East Antrim7.9
Loughmourne Roadwind turbinewind turbine—application submitted may be out of dateupdated Jun 2022Dec 2020—Jun 2022Mid and East Antrim8.6

Distance from the average position of the BT40 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm2010116.1
Wind turbine211000.3
Battery storage21100175

MW in pipeline: pending, approved and under-construction capacity.

How Mid and East Antrim decides solar, wind and battery applications

ApplicationsMid and East AntrimUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused0 of 612%
Onshore wind refused5 of 2245%
Battery storage refused0 of 216%
Median time from submission to decision45.2 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

All projects in Mid and East Antrim

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT40, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.