Energy Projects Near You

Quarterland Road, Islandmagee (75 MW battery storage)

Quarterland Road, Islandmagee is a 75 MW battery storage project in Mid and East Antrim, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 January 2024, not yet built; the record was last updated on 23 January 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

75 MWbattery storage
approved, not builtstatus in REPD
23 January 2024record last updated
Mid and East Antrimcouncil area

Planning timeline

DateStage
16 March 2023Application submitted
19 January 2024Planning permission granted
19 January 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
75 MW
Status (REPD)
approved, not built
Record last updated
23 January 2024
Operator or applicant
Solo Renewables Ltd
Planning authority
Mid and East Antrim
Planning application reference
LA02/2023/1283/F
Address (REPD)
Quarterland Road, Islandmagee
Council area (by location)
Mid and East Antrim
Time to decision
44 weeks
Name in REPD
Quarterland Road, Islandmagee - Battery Storage
REPD reference
14117

Who decides

ApplicationsMid and East AntrimUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused0 of 612%
Onshore wind refused5 of 2245%
Battery storage refused0 of 216%
Median time from submission to decision45.2 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Power Generation Development in Islandmageebattery storage100application submitted3.4
Ballykeel Wind Farmwind farm16.1approved, not built3.6
Mullaghsandall Road wind farmwind farm10refused on appeal7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8476, -5.7778).