Feystown Wind Farm (13.8 MW)
Feystown Wind Farm is a 13.8 MW wind farm project in Mid and East Antrim, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 6 July 2016; the record was last updated on 3 August 2016.
13.8 MWwind farm
refused on appealstatus in REPD
3 August 2016record last updated
Mid and East Antrimcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 14 May 2013 | Application submitted |
| 22 December 2014 | Refused by the planning authority |
| 27 March 2015 | Appeal lodged |
| 6 July 2016 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 13.8 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 3 August 2016
- Operator or applicant
- ABO Wind NI
- Planning authority
- Mid and East Antrim
- Planning application reference
- F/2013/0101/F
- Appeal reference
- 2014/A0285
- Turbines
- 6
- Address (REPD)
- Lands east of Feystown Road Glenarm; extending between an area situated approximately 750m east of 54 Feystown Road to lands adjacent to 92 Feystown Road. Within the townlands of Ault alias Gowkstown Clady and Dunteige Glenarm Co Antrim.
- Council area (by location)
- Mid and East Antrim
- Time to decision
- 84 weeks
- REPD reference
- 4237
Who decides
| Applications | Mid and East Antrim | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 30 | 10,236 |
| Refused | 5 (17%) | 19% |
| Solar refused | 0 of 6 | 12% |
| Onshore wind refused | 5 of 22 | 45% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 45.2 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Mullaghsandall Road wind farm | wind farm | 10 | refused on appeal | 8.0 |
| Unshinagh Wind Farm Development in Carnlough | wind farm | 58.8 | application submitted | 8.1 |
| Carnalbanagh Windfarm | wind farm | 21 | application submitted | 8.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9159, -5.9382).