Energy Projects Near You

Unshinagh Wind Farm Development in Carnlough (58.8 MW)

Unshinagh Wind Farm Development in Carnlough is a 58.8 MW wind farm project in Mid and East Antrim, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 22 December 2021, no decision recorded; the record was last updated on 25 July 2022. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

58.8 MWwind farm
application submittedmay be out of datestatus in REPD
25 July 2022record last updated
Mid and East Antrimcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
22 December 2021Application submitted

Project details

Technology
wind farm
Capacity
58.8 MW
Status (REPD)
application submitted
Record last updated
25 July 2022
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Mid and East Antrim
Planning application reference
LA02/2021/1205/F
Turbines
14
Turbine height
180 m
Address (REPD)
5km to the South West of the village of Carnlough, 5km west of Glenarm
Council area (by location)
Mid and East Antrim
REPD reference
11718

Who decides

ApplicationsMid and East AntrimUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused0 of 612%
Onshore wind refused5 of 2245%
Battery storage refused0 of 216%
Median time from submission to decision45.2 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carnalbanagh Windfarmwind farm21application submitted8.1
Feystown Wind Farmwind farm13.8refused on appeal8.1
Rathsherrywind farm21operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.968, -6.0267).