Energy Projects Near You

Elginny Hill (22 MW wind farm)

Elginny Hill is a 22 MW wind farm project in Mid and East Antrim, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2018; the record was last updated on 26 October 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWwind farm
operationalstatus in REPD
26 October 2018record last updated
Mid and East Antrimcouncil area

Planning timeline

DateStage
15 March 2011Application submitted
13 November 2014Planning permission granted
15 March 2017Construction started
15 March 2018Operational

Project details

Technology
wind farm
Capacity
22 MW
Status (REPD)
operational
Record last updated
26 October 2018
Operator or applicant
Brookfields (Antrim Wind Energy)
Planning authority
Mid and East Antrim
Planning application reference
G/2011/0041/F
Turbines
11
Address (REPD)
Carncoagh Hill, Elginny Hill, Clontrace Hill, Broughshane,
Council area (by location)
Mid and East Antrim
Time to decision
191 weeks
REPD reference
4563

Earlier applications for this site

ApplicationMWSubmittedOutcome
Elginny Hill G/2006/0754/F2021 September 2006withdrawn 17 January 2011

Who decides

ApplicationsMid and East AntrimUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused0 of 612%
Onshore wind refused5 of 2245%
Battery storage refused0 of 216%
Median time from submission to decision45.2 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rathsherrywind farm21operational2.4
Ballygarvey Roadsolar farm13operational6.7
Carnbuck Wind Farmwind farm50.4application submitted8.0
Carnalbanagh Windfarmwind farm21application submitted9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9326, -6.1929).