Energy Projects Near You

Carnbuck Wind Farm (50.4 MW)

Carnbuck Wind Farm is a 50.4 MW wind farm project in Mid and East Antrim, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 22 February 2023, no decision recorded; the record was last updated on 20 June 2023. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50.4 MWwind farm
application submittedmay be out of datestatus in REPD
20 June 2023record last updated
Mid and East Antrimcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
22 February 2023Application submitted

Project details

Technology
wind farm
Capacity
50.4 MW
Status (REPD)
application submitted
Record last updated
20 June 2023
Operator or applicant
RES Limited
Planning authority
Mid and East Antrim
Planning application reference
SPD/2023/0951/F
Turbines
12
Turbine height
180 m
Address (REPD)
Altnahinch Road, Ballymoney
Council area (by location)
Mid and East Antrim
REPD reference
14113

The scheme also includes battery storage, recorded separately in REPD (application submitted).

Who decides

ApplicationsMid and East AntrimUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused0 of 612%
Onshore wind refused5 of 2245%
Battery storage refused0 of 216%
Median time from submission to decision45.2 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gruig Wind Farmwind farm25operational3.4
Corkey Windfarm (repowering)wind farm20approved, not built4.0
Corkey Wind Farmwind farm5operational5.7
Rathsherrywind farm21operational6.9
Elginny Hillwind farm22operational8.0
Altaveedan Wind Farmwind farm17.9operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9975, -6.2475).