Altaveedan Wind Farm (17.9 MW)
Altaveedan Wind Farm is a 17.9 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 April 2017; the record was last updated on 1 December 2017.
17.9 MWwind farm
operationalstatus in REPD
1 December 2017record last updated
Causeway Coast and Glenscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 3 December 2010 | Application submitted |
| 28 October 2013 | Planning permission granted |
| 15 September 2015 | Construction started |
| 24 April 2017 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 17.9 MW
- Status (REPD)
- operational
- Record last updated
- 1 December 2017
- Operator or applicant
- NTR PLC
- Planning authority
- Causeway Coast and Glens
- Planning application reference
- D/2010/0356/F
- Turbines
- 9 (NTR; REPD: 6)
- Address (REPD)
- in the townlands of Shelton South, Aldorough, Altaveedan North, Altaveedan South and Turnavedog near Loughguile, Co Antrim
- Council area (by location)
- Causeway Coast and Glens
- Time to decision
- 151 weeks
- REPD reference
- 3850
Who decides
| Applications | Causeway Coast and Glens | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 6 (13%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 6 of 41 | 45% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 103.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Armoy Wind Farm | wind farm | 19.8 | refused on appeal | 4.5 |
| Corkey Wind Farm | wind farm | 5 | operational | 4.9 |
| Corkey Windfarm (repowering) | wind farm | 20 | approved, not built | 5.8 |
| Gruig Wind Farm | wind farm | 25 | operational | 7.5 |
| Cloonty Wind Farm | wind farm | 12 | operational | 9.6 |
| Carnbuck Wind Farm | wind farm | 50.4 | application submitted | 9.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0847, -6.2578).