Altaveedan Wind Farm (17.9 MW)

Altaveedan Wind Farm is a 17.9 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 April 2017; the record was last updated on 1 December 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17.9 MWwind farm
operationalstatus in REPD
1 December 2017record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
3 December 2010Application submitted
28 October 2013Planning permission granted
15 September 2015Construction started
24 April 2017Operational

Project details

Technology
wind farm
Capacity
17.9 MW
Status (REPD)
operational
Record last updated
1 December 2017
Operator or applicant
NTR PLC
Planning authority
Causeway Coast and Glens
Planning application reference
D/2010/0356/F
Turbines
9 (NTR; REPD: 6)
Address (REPD)
in the townlands of Shelton South, Aldorough, Altaveedan North, Altaveedan South and Turnavedog near Loughguile, Co Antrim
Council area (by location)
Causeway Coast and Glens
Time to decision
151 weeks
REPD reference
3850

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Armoy Wind Farmwind farm19.8refused on appeal4.5
Corkey Wind Farmwind farm5operational4.9
Corkey Windfarm (repowering)wind farm20approved, not built5.8
Gruig Wind Farmwind farm25operational7.5
Cloonty Wind Farmwind farm12operational9.6
Carnbuck Wind Farmwind farm50.4application submitted9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0847, -6.2578).