Armoy Wind Farm (19.8 MW)

Armoy Wind Farm is a 19.8 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 8 January 2020; the record was last updated on 27 March 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.8 MWwind farm
refused on appealstatus in REPD
27 March 2020record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
22 December 2017Application submitted
24 January 2019Appeal lodged
8 January 2020Appeal refused

Project details

Technology
wind farm
Capacity
19.8 MW
Status (REPD)
refused on appeal
Record last updated
27 March 2020
Operator or applicant
ABO Wind NI
Planning authority
Causeway Coast and Glens
Planning application reference
LA01/2017/1654/F
Appeal reference
2018/A0199
Turbines
6
Turbine height
150 m
Address (REPD)
Lands approx. 615m East of, 16 Coolkeeran Road, Armoy, 2.5km South East of Armoy, Ballymoney, Co Antrim
Council area (by location)
Causeway Coast and Glens
REPD reference
6546

The scheme also includes battery storage, recorded separately in REPD (refused on appeal).

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Altaveedan Wind Farmwind farm17.9operational4.5
Cloonty Wind Farmwind farm12operational5.8
Corkey Wind Farmwind farm5operational8.0
Carneatlywind farm9.2application withdrawn8.8
Corkey Windfarm (repowering)wind farm20approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1145, -6.3056).