Energy Projects Near You

Renewable energy projects in Causeway Coast and Glens

68 solar, wind or battery projects of 150 kW or more are located in Causeway Coast and Glens (REPD, July 2026 extract): 13 pending, 20 approved but not running, 22 operational and 2 refused. The council refused 6 of 47 decided applications (13%; UK 19%), with a median 103 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

68projects in the council area
13awaiting a decision
20approved, not running
13%of decisions refused

How Causeway Coast and Glens decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Projects in Causeway Coast and Glens

Projects of 1 MW and more (45)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Energy Storage System Installation in Rasharkinbattery storagebattery storage100application submittedupdated Apr 2025Feb 2025—Apr 2025
Windy Hillwind farmwind farm52.5appeal withdrawnupdated Aug 2015Jul 2013—Aug 2015
Farklandwind farmwind farm51application withdrawnupdated Mar 2011Dec 2007—Mar 2011
Evishagaran Wind Farmwind farmwind farm46.8approved, not built may be out of dateupdated Feb 2020Sep 2018granted Apr 2019Feb 2020
Windyhill Road (Dunbeg) Wind Farmwind farmwind farm42operationalupdated Jan 2017Dec 2007granted Jan 2011Jan 2017
Brockaghboy Wind Farmwind farmwind farm37.5operationalupdated Apr 2018Dec 2007granted Jan 2012Apr 2018
Dunbeg South Wind Farmwind farmwind farm29.7approved, not built may be out of dateupdated Jun 2026Feb 2018granted Dec 2020Jun 2026
Brishey Wind Farmwind farmwind farm28.8application submitted may be out of dateupdated Apr 2023Jan 2023—Apr 2023
Rigged Hill Wind Farm (Repowering)wind farmwind farm28approved, not builtupdated Oct 2022Aug 2019granted Oct 2022Oct 2022
Slieve Kirk (formerly Altahullion Phase III & Glenconway 2)wind farmwind farm27.6operationalupdated Dec 2013Jan 2007granted Sep 2010Dec 2013
Long Mountainwind farmwind farm27.6operationalupdated Jan 2017Mar 2006granted Jan 2007Jan 2017
Altahullionwind farmwind farm26operationalupdated Feb 2010Jun 2001granted Oct 2001Feb 2010
Gruig Wind Farmwind farmwind farm25operationalupdated Nov 2019Oct 2004granted Jun 2007Nov 2019
Bann Road (Tullaghans Road)solar farmsolar farm25operationalupdated Dec 2017Dec 2015granted Aug 2016Dec 2017
Dunmore Wind Farm - extensionwind farmwind farm24approved, not built may be out of dateupdated Nov 2019Nov 2013granted Jun 2018Nov 2019
Dungivenwind farmwind farm24approved, not builtupdated Nov 2025Aug 2019granted Jul 2025Nov 2025
Craiggore windfarmwind farmwind farm23.5operationalupdated Feb 2024Oct 2012granted Mar 2015Feb 2024
Dunmorewind farmwind farm21operationalupdated Aug 2013Dec 2007granted Oct 2010Aug 2013
Corkey Windfarm (repowering)wind farmwind farm20approved, not built may be out of dateupdated Mar 2022Jul 2019granted Mar 2022Mar 2022
Armoy Wind Farmwind farmwind farm19.8refused on appealupdated Mar 2020Dec 2017—Mar 2020
Slieve Kirk (formerly Glenconway)wind farmwind farm18.4operationalupdated Dec 2013Dec 2006granted Feb 2009Dec 2013
Bann Road (Rasharkin)solar farmsolar farm18operationalupdated Nov 2017Sep 2014—Nov 2017
Altaveedan Wind Farmwind farmwind farm17.9operationalupdated Dec 2017Dec 2010granted Oct 2013Dec 2017
Dunbeg South Wind Farm - Extensionwind farmwind farm16.8application submittedupdated Jun 2026Nov 2024—Jun 2026
Smulgedonwind farmwind farm16.1abandonedupdated Dec 2017Feb 2009granted Oct 2012Dec 2017
Garves Mountain Farmwind farmwind farm15operationalupdated Dec 2017Jun 2003granted Nov 2006Dec 2017
Cam Burn Wind Farmwind farmwind farm13.8abandonedupdated Nov 2019Sep 2011granted Dec 2016Nov 2019
Croaghanwind farmwind farm12.5application withdrawnupdated Oct 2018Apr 2011—Oct 2018
Cloonty Wind Farmwind farmwind farm12operationalupdated Jan 2017Jun 2009granted Mar 2013Jan 2017
Altahullion Phase IIwind farmwind farm11.7operationalupdated Jan 2019Nov 2004granted Apr 2006Jan 2019
Upper Ballyrogan Wind Farmwind farmwind farm11.5abandonedupdated Mar 2018Jul 2012granted Apr 2013Mar 2018
Brockaghboy Wind Farm - extensionwind farmwind farm10operationalupdated Apr 2018Jun 2014granted Oct 2015Apr 2018
Carneatlywind farmwind farm9.2application withdrawnupdated Jul 2018Apr 2011—Jul 2018
Dunbeg Extensionwind farmwind farm9approved, not built may be out of dateupdated May 2020Dec 2015granted Apr 2017May 2020
62 Muldonagh Road, Claudywind turbinewind turbine8.8application submitted may be out of dateupdated Nov 2023Jun 2023—Nov 2023
Glenbuckwind farmwind farm6.9operationalupdated Dec 2017Nov 2006granted Jun 2011Dec 2017
Lisnamuck Wind Farmwind farmwind farm6application withdrawnupdated Apr 2011Feb 2008—Apr 2011
Finvoy Roadsolar farmsolar farm5.9operationalupdated Dec 2017Dec 2014granted Aug 2015Dec 2017
Corkey Wind Farmwind farmwind farm5operationalupdated Aug 2017Nov 1993granted Jun 1994Aug 2017
Rigged Hill Wind Farmwind farmwind farm5operationalupdated Aug 2017Nov 1993granted Jul 1994Aug 2017
Craigs Wind Turbine IIwind turbinewind turbine3permission expiredupdated Nov 2019Nov 2015granted Jan 2017Nov 2019
Corkey Wind Farm Extensionwind turbinewind turbine2.5operationalupdated Jul 2017Feb 2010granted Feb 2012Jul 2017
Glenbuckwind turbinewind turbine2.3operationalupdated Dec 2016Jun 2005granted Apr 2007Dec 2016
Shinny Road Macosquinsolar farmsolar farm1application submitted may be out of dateupdated Mar 2020Mar 2020—Mar 2020
Battery Energy Storage System in Ballycastlebattery storagebattery storage1approved, not builtupdated Apr 2024Nov 2023granted Mar 2024Apr 2024
Smaller schemes under 1 MW, mostly rooftop solar (23)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Ballindreen Roadwind turbinewind turbine0.5approved, not builtupdated Aug 2025Aug 2024granted Jun 2025Aug 2025
Islandranny Roadwind turbinewind turbine0.3approved, not built may be out of dateupdated Nov 2019Dec 2018granted Jun 2019Nov 2019
Dullaghy Roadwind turbinewind turbine0.3application withdrawnupdated Mar 2020Mar 2019—Mar 2020
Mullan Roadwind turbinewind turbine0.3approved, not built may be out of dateupdated Apr 2022Mar 2020granted Jun 2021Apr 2022
Terrydoo Road 1wind turbinewind turbine0.3approved, not built may be out of dateupdated Jun 2020Mar 2020granted Nov 2022Jun 2020
Stroan Roadwind turbinewind turbine0.3approved, not builtupdated Jun 2020May 2020granted Jun 2022Jun 2020
Terrydoo Road 2wind turbinewind turbine0.3approved, not builtupdated Jun 2020Mar 2020granted Nov 2022Jun 2020
Curragh Roadwind turbinewind turbine0.3approved, not builtupdated Sep 2020Aug 2020granted Mar 2022Sep 2020
Moyarget Roadwind turbinewind turbine0.3approved, not builtupdated Sep 2020Jun 2020granted Apr 2022Sep 2020
Moyarget Roadwind turbinewind turbine0.2application submitted may be out of dateupdated Apr 2022Nov 2020—Apr 2022
Wind Turbine Development in Ballymoneywind turbinewind turbine0.2application withdrawnupdated Jan 2026Jan 2025—Jan 2026
Windyhill Roadwind turbinewind turbine0.2approved, not built may be out of dateupdated Apr 2021Oct 2019granted Nov 2020Apr 2021
Reservoir Roadwind turbinewind turbine0.2application submitted may be out of dateupdated Mar 2020Jan 2020—Mar 2020
Lidl Nutts Cornerrooftop solarrooftop solar0.2application submitted may be out of dateupdated Jun 2020Jun 2020—Jun 2020
Armoy Wind Farmbattery storagebattery storage—refused on appealupdated Mar 2020Dec 2017—Mar 2020
Ballyavelin Road Replacement Turbinewind turbinewind turbine—application submitted may be out of dateupdated Mar 2021Feb 2021—Mar 2021
Drumack Lane Replacement Turbinewind turbinewind turbine—approved, not builtupdated Mar 2021Feb 2021granted Feb 2022Mar 2021
Power Generation Development in Colerainesolar farmsolar farm—application submitted may be out of dateupdated Feb 2022Nov 2021—Feb 2022
Finvoy Road, Rasharkinbattery storagebattery storage—approved, not builtupdated Sep 2024Mar 2023granted Aug 2024Sep 2024
Solar PV Energy Development in Ballycastlesolar farmsolar farm—approved, not builtupdated Oct 2024Mar 2024granted Oct 2024Oct 2024
Turbine Development in Garvaghwind turbinewind turbine—application submittedupdated Mar 2025Jan 2025—Mar 2025
Moyarget Roadwind turbinewind turbine—application submittedupdated May 2025Mar 2025—May 2025
Shinny Road, Macosquinwind turbinewind turbine—application submitted may be out of dateupdated Mar 2026Oct 2023—Mar 2026

Postcode districts in Causeway Coast and Glens

DistrictProjects within 10 kmPendingApprovedOperational
BT4416348
BT4914365
BT5112332
BT525220
BT537024
BT547230
BT552010
BT561010
BT572020

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Causeway Coast and Glens by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.