Energy Projects Near You

Solar, wind and battery projects near Bushmills (BT57)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT57 (Causeway Coast and Glens): 2 approved but not yet running. The largest live scheme is Ballindreen Road (0.5 MW wind turbine, approved on 23 June 2025, not yet built), 9.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
2approved, not running
0operational

Projects within 10 km of BT57

Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Islandranny Roadwind turbinewind turbine0.3approved, not built may be out of dateupdated Nov 2019Dec 2018granted Jun 2019Nov 2019Causeway Coast and Glens5.2
Ballindreen Roadwind turbinewind turbine0.5approved, not builtupdated Aug 2025Aug 2024granted Jun 2025Aug 2025Causeway Coast and Glens9.7

Distance from the average position of the BT57 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind turbine202000.8

MW in pipeline: pending, approved and under-construction capacity.

How Causeway Coast and Glens decides solar, wind and battery applications

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

All projects in Causeway Coast and Glens

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT57, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.