Energy Projects Near You

Solar, wind and battery projects near Portrush (BT56)

1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of BT56 (Causeway Coast and Glens): 1 approved but not yet running. The largest live scheme is Ballindreen Road (0.5 MW wind turbine, approved on 23 June 2025, not yet built), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1projects within 10 km
0awaiting a decision
1approved, not running
0operational

Projects within 10 km of BT56

Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ballindreen Roadwind turbinewind turbine0.5approved, not builtupdated Aug 2025Aug 2024granted Jun 2025Aug 2025Causeway Coast and Glens9.5

Distance from the average position of the BT56 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind turbine101000.5

MW in pipeline: pending, approved and under-construction capacity.

How Causeway Coast and Glens decides solar, wind and battery applications

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

All projects in Causeway Coast and Glens

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.