Energy Projects Near You

Solar, wind and battery projects near Coleraine (BT52)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT52 (Causeway Coast and Glens): 2 are waiting for a planning decision, 2 approved but not yet running. The largest live scheme is Ballindreen Road (0.5 MW wind turbine, approved on 23 June 2025, not yet built), 5.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
2awaiting a decision
2approved, not running
0operational

Projects within 10 km of BT52

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Croaghanwind farmwind farm12.5application withdrawnupdated Oct 2018Apr 2011—Oct 2018Causeway Coast and Glens9.5
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ballindreen Roadwind turbinewind turbine0.5approved, not builtupdated Aug 2025Aug 2024granted Jun 2025Aug 2025Causeway Coast and Glens5.1
Power Generation Development in Colerainesolar farmsolar farm—application submitted may be out of dateupdated Feb 2022Nov 2021—Feb 2022Causeway Coast and Glens7.9
Windyhill Roadwind turbinewind turbine0.2approved, not built may be out of dateupdated Apr 2021Oct 2019granted Nov 2020Apr 2021Causeway Coast and Glens8.5
Shinny Road, Macosquinwind turbinewind turbine—application submitted may be out of dateupdated Mar 2026Oct 2023—Mar 2026Causeway Coast and Glens8.8

Distance from the average position of the BT52 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm110000
Wind farm100000
Wind turbine312000.7

MW in pipeline: pending, approved and under-construction capacity.

How Causeway Coast and Glens decides solar, wind and battery applications

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

All projects in Causeway Coast and Glens

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT52, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.