Dunbeg South Wind Farm (29.7 MW)

Dunbeg South Wind Farm is a 29.7 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 December 2020, not yet built; the record was last updated on 8 June 2026. REPD also records that the planning permission expired on 17 December 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.7 MWwind farm
approved, not builtmay be out of datestatus in REPD
8 June 2026record last updated
Causeway Coast and Glenscouncil area

REPD also records that the planning permission expired on 17 December 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
19 February 2018Application submitted
17 December 2020Planning permission granted
17 December 2025Permission expired

Project details

Technology
wind farm
Capacity
29.7 MW
Status (REPD)
approved, not built
Record last updated
8 June 2026
Operator or applicant
Renewable Energy Systems (RES) / Innagreen Investments
Planning authority
Causeway Coast and Glens
Planning application reference
LA01/2018/0200/F
Turbines
9
Turbine height
150 m
Address (REPD)
Lands approx 6km N E of, Limavady Road, Derry, Co Londonderry
Council area (by location)
Causeway Coast and Glens
Time to decision
147 weeks
REPD reference
6562

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dunbeg South Wind Farm - Extensionwind farm16.8application submitted<0.1
Dunbeg Extensionwind farm9approved, not built1.9
Dunmore Wind Farm - extensionwind farm24approved, not built2.1
Dunmorewind farm21operational2.1
Windyhill Road (Dunbeg) Wind Farmwind farm42operational2.4
Rigged Hill Wind Farm (Repowering)wind farm28approved, not built5.5
Rigged Hill Wind Farmwind farm5operational5.8
Croaghanwind farm12.5application withdrawn5.8
Windy Hillwind farm52.5appeal withdrawn7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0694, -6.8555).