Dunmore Wind Farm - extension (24 MW)
Dunmore Wind Farm - extension is a 24 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 June 2018, not yet built; the record was last updated on 21 November 2019. REPD also records that the planning permission expired on 15 June 2023, so the project may not go ahead in this form. Check the planning authority's register for the latest position.
REPD also records that the planning permission expired on 15 June 2023, so the project may not go ahead in this form.
Planning timeline
| Date | Stage |
|---|---|
| 27 November 2013 | Application submitted |
| 28 April 2017 | Refused by the planning authority |
| 15 November 2017 | Appeal lodged |
| 15 June 2018 | Planning permission granted |
| 15 June 2018 | Appeal allowed |
| 15 June 2023 | Permission expired |
Project details
- Technology
- wind farm
- Capacity
- 24 MW
- Status (REPD)
- approved, not built
- Record last updated
- 21 November 2019
- Operator or applicant
- TCI Renewables
- Planning authority
- Causeway Coast and Glens
- Planning application reference
- B/2013/0241/F
- Appeal reference
- 2017/A0023
- Turbines
- 8
- Address (REPD)
- Largantea and Dunmore townlands Bolea Road 8km north-east of Limavady
- Council area (by location)
- Causeway Coast and Glens
- Time to decision
- 237 weeks
- REPD reference
- 4301
Who decides
| Applications | Causeway Coast and Glens | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 6 (13%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 6 of 41 | 45% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 103.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Dunmore | wind farm | 21 | operational | <0.1 |
| Windyhill Road (Dunbeg) Wind Farm | wind farm | 42 | operational | 1.3 |
| Dunbeg Extension | wind farm | 9 | approved, not built | 1.5 |
| Dunbeg South Wind Farm | wind farm | 29.7 | approved, not built | 2.1 |
| Dunbeg South Wind Farm - Extension | wind farm | 16.8 | application submitted | 2.1 |
| Rigged Hill Wind Farm (Repowering) | wind farm | 28 | approved, not built | 6.5 |
| Rigged Hill Wind Farm | wind farm | 5 | operational | 6.8 |
| Croaghan | wind farm | 12.5 | application withdrawn | 7.9 |
| Windy Hill | wind farm | 52.5 | appeal withdrawn | 8.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0687, -6.889).