Dunmore (21 MW wind farm)

Dunmore is a 21 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 April 2013; the record was last updated on 16 August 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWwind farm
operationalstatus in REPD
16 August 2013record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
12 December 2007Application submitted
24 April 2009Refused by the planning authority
29 October 2010Planning permission granted
29 October 2010Appeal allowed
25 April 2013Operational

Project details

Technology
wind farm
Capacity
21 MW
Status (REPD)
operational
Record last updated
16 August 2013
Operator or applicant
TCI Renewables
Planning authority
Causeway Coast and Glens
Planning application reference
not recorded
Turbines
7
Address (REPD)
Town land of Dunmore approximately eight kilometres north east of Limavady, County Londonderry
Council area (by location)
Causeway Coast and Glens
Time to decision
150 weeks
REPD reference
3969

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dunmore Wind Farm - extensionwind farm24approved, not built<0.1
Windyhill Road (Dunbeg) Wind Farmwind farm42operational1.3
Dunbeg Extensionwind farm9approved, not built1.5
Dunbeg South Wind Farmwind farm29.7approved, not built2.1
Dunbeg South Wind Farm - Extensionwind farm16.8application submitted2.1
Rigged Hill Wind Farm (Repowering)wind farm28approved, not built6.5
Rigged Hill Wind Farmwind farm5operational6.8
Croaghanwind farm12.5application withdrawn7.9
Windy Hillwind farm52.5appeal withdrawn8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0687, -6.889).