Long Mountain (27.6 MW wind farm)

Long Mountain is a 27.6 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 December 2016; the record was last updated on 4 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27.6 MWwind farm
operationalstatus in REPD
4 January 2017record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
8 March 2006Application submitted
5 January 2007Planning permission granted
15 January 2016Construction started
15 December 2016Operational

Project details

Technology
wind farm
Capacity
27.6 MW
Status (REPD)
operational
Record last updated
4 January 2017
Operator or applicant
Energia Renewables
Planning authority
Causeway Coast and Glens
Planning application reference
D/2006/0104/F
Turbines
12
Address (REPD)
Dunloy, Co. Antrim
Council area (by location)
Causeway Coast and Glens
Time to decision
43 weeks
REPD reference
4652

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bann Road (Tullaghans Road)solar farm25operational1.6
Energy Storage System Installation in Rasharkinbattery storage100application submitted2.8
Glenbuckwind farm6.9operational3.5
Finvoy Roadsolar farm5.9operational4.0
Bann Road (Rasharkin)solar farm18operational5.4
Garves Mountain Farmwind farm15operational8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9841, -6.442).