Energy Projects Near You

Energy Storage System Installation in Rasharkin (100 MW)

Energy Storage System Installation in Rasharkin is a 100 MW battery storage project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 28 February 2025, no decision recorded; the record was last updated on 4 April 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
application submittedstatus in REPD
4 April 2025record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
28 February 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
application submitted
Record last updated
4 April 2025
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Causeway Coast and Glens
Planning application reference
LA01/2025/0181/F
Address (REPD)
340m South of 5 Magheraboy Road, Rasharkin
Council area (by location)
Causeway Coast and Glens
REPD reference
18463

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Finvoy Roadsolar farm5.9operational1.2
Bann Road (Rasharkin)solar farm18operational2.6
Long Mountainwind farm27.6operational2.8
Bann Road (Tullaghans Road)solar farm25operational3.9
Glenbuckwind farm6.9operational6.1
Garves Mountain Farmwind farm15operational6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9713, -6.4793).