Energy Projects Near You

Bann Road (Tullaghans Road) (25 MW solar farm)

Bann Road (Tullaghans Road) is a 25 MW solar farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2017; the record was last updated on 4 December 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
operationalstatus in REPD
4 December 2017record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
14 December 2015Application submitted
4 August 2016Planning permission granted
12 December 2016Construction started
15 February 2017Operational

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
operational
Record last updated
4 December 2017
Operator or applicant
Greencoat Capital
Planning authority
Causeway Coast and Glens
Planning application reference
LA01/2015/1045/F
Site area
49.0 ha
Address (REPD)
Lands surrounding 25 and 25(a), Tullaghans Road, Mullans 360m Southeast of 190, 430m South of 27 Tullaghans Ro, Ballymena
Council area (by location)
Causeway Coast and Glens
Time to decision
33 weeks
REPD reference
5955

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Long Mountainwind farm27.6operational1.6
Glenbuckwind farm6.9operational2.2
Energy Storage System Installation in Rasharkinbattery storage100application submitted3.9
Finvoy Roadsolar farm5.9operational5.1
Bann Road (Rasharkin)solar farm18operational6.4
Garves Mountain Farmwind farm15operational7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9985, -6.4404).