Craiggore windfarm (23.5 MW)

Craiggore windfarm is a 23.5 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational; the record was last updated on 15 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23.5 MWwind farm
operationalstatus in REPD
15 February 2024record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
15 October 2012Application submitted
5 March 2015Planning permission granted
19 September 2019Construction started

Project details

Technology
wind farm
Capacity
23.5 MW
Status (REPD)
operational
Record last updated
15 February 2024
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Causeway Coast and Glens
Planning application reference
B/2012/0268/F
Turbines
10
Address (REPD)
Craiggore windfarm in the townlands of Moneyguiggy and Craiggore Forest Belraugh Road Co Londonderry
Council area (by location)
Causeway Coast and Glens
Time to decision
124 weeks
REPD reference
4297

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Upper Ballyrogan Wind Farmwind farm11.5abandoned2.6
Brockaghboy Wind Farmwind farm37.5operational2.8
Rigged Hill Wind Farmwind farm5operational3.2
Rigged Hill Wind Farm (Repowering)wind farm28approved, not built3.5
Smulgedonwind farm16.1abandoned6.0
Brishey Wind Farmwind farm28.8application submitted7.4
Evishagaran Wind Farmwind farm46.8approved, not built7.8
Cam Burn Wind Farmwind farm13.8abandoned8.0
Brockaghboy Wind Farm (Further Extension)wind farm10approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9952, -6.8011).