Upper Ballyrogan Wind Farm (11.5 MW)

Upper Ballyrogan Wind Farm is an 11.5 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 15 March 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.5 MWwind farm
abandonedstatus in REPD
15 March 2018record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
10 July 2012Application submitted
11 April 2013Planning permission granted
11 April 2018Permission expired

Project details

Technology
wind farm
Capacity
11.5 MW
Status (REPD)
abandoned
Record last updated
15 March 2018
Operator or applicant
TCI Renewables
Planning authority
Causeway Coast and Glens
Planning application reference
C/2012/0276/F
Turbines
5
Address (REPD)
land approximately 870m west of 40 Ballyrogan Road Garvagh Co Londonderry BT51 5EY
Council area (by location)
Causeway Coast and Glens
Time to decision
39 weeks
REPD reference
4423

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brockaghboy Wind Farmwind farm37.5operational1.7
Craiggore windfarmwind farm23.5operational2.6
Rigged Hill Wind Farmwind farm5operational4.8
Rigged Hill Wind Farm (Repowering)wind farm28approved, not built5.1
Cam Burn Wind Farmwind farm13.8abandoned6.2
Brockaghboy Wind Farm (Further Extension)wind farm10approved, not built7.7
Smulgedonwind farm16.1abandoned7.9
Lisnamuck Wind Farmwind farm6application withdrawn8.4
Brishey Wind Farmwind farm28.8application submitted9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9955, -6.7597).