Upper Ballyrogan Wind Farm (11.5 MW)
Upper Ballyrogan Wind Farm is an 11.5 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 15 March 2018.
11.5 MWwind farm
abandonedstatus in REPD
15 March 2018record last updated
Causeway Coast and Glenscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 10 July 2012 | Application submitted |
| 11 April 2013 | Planning permission granted |
| 11 April 2018 | Permission expired |
Project details
- Technology
- wind farm
- Capacity
- 11.5 MW
- Status (REPD)
- abandoned
- Record last updated
- 15 March 2018
- Operator or applicant
- TCI Renewables
- Planning authority
- Causeway Coast and Glens
- Planning application reference
- C/2012/0276/F
- Turbines
- 5
- Address (REPD)
- land approximately 870m west of 40 Ballyrogan Road Garvagh Co Londonderry BT51 5EY
- Council area (by location)
- Causeway Coast and Glens
- Time to decision
- 39 weeks
- REPD reference
- 4423
Who decides
| Applications | Causeway Coast and Glens | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 6 (13%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 6 of 41 | 45% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 103.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Brockaghboy Wind Farm | wind farm | 37.5 | operational | 1.7 |
| Craiggore windfarm | wind farm | 23.5 | operational | 2.6 |
| Rigged Hill Wind Farm | wind farm | 5 | operational | 4.8 |
| Rigged Hill Wind Farm (Repowering) | wind farm | 28 | approved, not built | 5.1 |
| Cam Burn Wind Farm | wind farm | 13.8 | abandoned | 6.2 |
| Brockaghboy Wind Farm (Further Extension) | wind farm | 10 | approved, not built | 7.7 |
| Smulgedon | wind farm | 16.1 | abandoned | 7.9 |
| Lisnamuck Wind Farm | wind farm | 6 | application withdrawn | 8.4 |
| Brishey Wind Farm | wind farm | 28.8 | application submitted | 9.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9955, -6.7597).