Slieve Kirk (formerly Glenconway) (18.4 MW wind farm)

Slieve Kirk (formerly Glenconway) is an 18.4 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 November 2013; the record was last updated on 12 December 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.4 MWwind farm
operationalstatus in REPD
12 December 2013record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
15 December 2006Application submitted
17 February 2009Planning permission granted
14 May 2012Construction started
7 November 2013Operational

Project details

Technology
wind farm
Capacity
18.4 MW
Status (REPD)
operational
Record last updated
12 December 2013
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Causeway Coast and Glens
Planning application reference
B/2006/0607/F
Turbines
8
Address (REPD)
Land at Glenconway Hill off Baranailt Road, (Adjacent to Loughermore Forest and north of Altahullion windfarm), Limavady.
Council area (by location)
Causeway Coast and Glens
Time to decision
114 weeks
REPD reference
3953

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Slieve Kirk (formerly Altahullion Phase III & Glenconway 2)wind farm27.6operational0.7
Altahullionwind farm26operational1.5
Altahullion Phase IIwind farm11.7operational2.0
Farklandwind farm51application withdrawn4.2
Monnaboy Wind Farm Ext.wind farm6application withdrawn5.4
62 Muldonagh Road, Claudywind turbine8.8application submitted5.5
Monnaboy Wind Farmwind farm12operational6.7
Ballyhanedin Wind Farmwind farm24approved, not built8.0
Barr Cregg Wind Farmwind farm12.6approved, not built8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.976, -7.0296).