62 Muldonagh Road, Claudy (8.8 MW wind turbine)
62 Muldonagh Road, Claudy is an 8.8 MW wind turbine project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 19 June 2023, no decision recorded; the record was last updated on 1 November 2023. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.
The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.
Planning timeline
| Date | Stage |
|---|---|
| 19 June 2023 | Application submitted |
Project details
- Technology
- wind turbine
- Capacity
- 8.8 MW
- Status (REPD)
- application submitted
- Record last updated
- 1 November 2023
- Operator or applicant
- Unknown
- Planning authority
- Causeway Coast and Glens
- Planning application reference
- LA11/2023/1754/F
- Turbines
- 1
- Turbine height
- 119 m
- Address (REPD)
- 1000m North of 62 Muldonagh Road, Claudy
- Council area (by location)
- Causeway Coast and Glens
- Name in REPD
- 62 Muldonagh Road, Claudy - Wind Turbine
- REPD reference
- 15152
Who decides
| Applications | Causeway Coast and Glens | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 6 (13%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 6 of 41 | 45% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 103.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Farkland | wind farm | 51 | application withdrawn | 1.9 |
| Ballyhanedin Wind Farm | wind farm | 24 | approved, not built | 3.5 |
| Altahullion | wind farm | 26 | operational | 4.1 |
| Slieve Kirk (formerly Altahullion Phase III & Glenconway 2) | wind farm | 27.6 | operational | 4.8 |
| Barr Cregg Wind Farm | wind farm | 12.6 | approved, not built | 5.0 |
| Slieve Kirk (formerly Glenconway) | wind farm | 18.4 | operational | 5.5 |
| Monnaboy Wind Farm Ext. | wind farm | 6 | application withdrawn | 6.1 |
| Altahullion Phase II | wind farm | 11.7 | operational | 6.2 |
| Monnaboy Wind Farm | wind farm | 12 | operational | 6.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9321, -7.0699).