Energy Projects Near You

Monnaboy Wind Farm (12 MW)

Monnaboy Wind Farm is a 12 MW wind farm project in Derry City and Strabane, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 November 2015; the record was last updated on 3 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
operationalstatus in REPD
3 January 2017record last updated
Derry City and Strabanecouncil area

Planning timeline

DateStage
6 November 2009Application submitted
12 October 2012Planning permission granted
15 January 2015Construction started
15 November 2015Operational

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
3 January 2017
Operator or applicant
Gaelectric Developments/ CGN Europe Energy
Planning authority
Derry City and Strabane
Planning application reference
A/2009/0868/F
Turbines
4
Address (REPD)
on land located east of 62 Monnaboy Road, Greysteel
Council area (by location)
Derry City and Strabane
Time to decision
153 weeks
REPD reference
4155

Who decides

ApplicationsDerry City and StrabaneUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused0 of 212%
Onshore wind refused10 of 4345%
Battery storage refused0 of 416%
Median time from submission to decision103.3 weeks17.0 weeks
Appeals lodged / allowed4 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Monnaboy Wind Farm Ext.wind farm6application withdrawn1.3
Barr Cregg Wind Farmwind farm12.6approved, not built3.8
Slieve Kirk (formerly Altahullion Phase III & Glenconway 2)wind farm27.6operational6.4
62 Muldonagh Road, Claudywind turbine8.8application submitted6.6
Altahullionwind farm26operational6.6
Slieve Kirk (formerly Glenconway)wind farm18.4operational6.7
Farklandwind farm51application withdrawn7.3
Power Generation in Development in Claudybattery storage75application submitted7.6
Battery Energy Storage Facility in Londonderrybattery storage34approved, not built7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9791, -7.1341).