Power Generation in Development in Claudy (75 MW battery storage)

Power Generation in Development in Claudy is a 75 MW battery storage project in Derry City and Strabane, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 21 December 2022, no decision recorded; the record was last updated on 8 December 2025. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

75 MWbattery storage
application submittedmay be out of datestatus in REPD
8 December 2025record last updated
Derry City and Strabanecouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
21 December 2022Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
75 MW
Status (REPD)
application submitted
Record last updated
8 December 2025
Operator or applicant
Ballyarton Energy Limited
Planning authority
Derry City and Strabane
Planning application reference
LA11/2022/1182/F
Address (REPD)
Lands 85M Northeast Of No. 10 Gortnaran Road, Claudy
Council area (by location)
Derry City and Strabane
REPD reference
19970

Who decides

ApplicationsDerry City and StrabaneUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused0 of 212%
Onshore wind refused10 of 4345%
Battery storage refused0 of 416%
Median time from submission to decision103.3 weeks17.0 weeks
Appeals lodged / allowed4 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Townlands of Carrickatanewind farm20.7operational2.7
Barr Cregg Wind Farmwind farm12.6approved, not built4.1
Eglish Mountainwind farm13.8operational4.2
Slieve Kirkwind farm27.6operational6.7
Slieve Kirk Extwind farm11.5permission expired6.7
62 Muldonagh Road, Claudywind turbine8.8application submitted7.5
Monnaboy Wind Farmwind farm12operational7.6
Monnaboy Wind Farm Ext.wind farm6application withdrawn8.4
Curryfree Wind Farmwind farm15operational8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9171, -7.184).