Curryfree Wind Farm (15 MW)

Curryfree Wind Farm is a 15 MW wind farm project in Derry City and Strabane, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 August 2011; the record was last updated on 24 October 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
operationalstatus in REPD
24 October 2011record last updated
Derry City and Strabanecouncil area

Planning timeline

DateStage
24 November 2004Application submitted
12 May 2008Planning permission granted
1 December 2009Construction started
1 August 2011Operational

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
24 October 2011
Operator or applicant
ESB
Planning authority
Derry City and Strabane
Planning application reference
A/2004/1243/F
Turbines
6
Address (REPD)
Curryfree , South of Newbuildings / Drumahoe and north of Dunamanagh, Co. Londonderry
Council area (by location)
Derry City and Strabane
Time to decision
181 weeks
REPD reference
3243

Who decides

ApplicationsDerry City and StrabaneUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused0 of 212%
Onshore wind refused10 of 4345%
Battery storage refused0 of 416%
Median time from submission to decision103.3 weeks17.0 weeks
Appeals lodged / allowed4 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Slieve Kirkwind farm27.6operational2.0
Slieve Kirk Extwind farm11.5permission expired2.0
Trench Road, Killymallaght Substationbattery storage50application submitted2.1
Gortmonly Wind Energywind farm15application withdrawn4.3
Ballylawwind farm6.9application withdrawn7.6
Mullaghmeash Road & Feenybattery storage100application submitted7.7
Eglish Mountainwind farm13.8operational8.3
Townlands of Carrickatanewind farm20.7operational8.4
Power Generation in Development in Claudybattery storage75application submitted8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9293, -7.3167).