Eglish Mountain (13.8 MW wind farm)

Eglish Mountain is a 13.8 MW wind farm project in Derry City and Strabane, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 13 January 2017; the record was last updated on 30 June 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.8 MWwind farm
operationalstatus in REPD
30 June 2017record last updated
Derry City and Strabanecouncil area

Planning timeline

DateStage
1 February 2005Application submitted
29 July 2013Planning permission granted
25 October 2015Construction started
13 January 2017Operational

Project details

Technology
wind farm
Capacity
13.8 MW
Status (REPD)
operational
Record last updated
30 June 2017
Operator or applicant
ESB (Northern Wind Power)
Planning authority
Derry City and Strabane
Planning application reference
A/2005/0223/F
Turbines
6
Address (REPD)
Eglish Mountain in the townlands of Ballyartan and Glenlough (Co. Derry) and Ballyneaner (Co. Tyrone), accessing onto Ballyartan Road, Killaloo, Londonderry BT47 3TA
Council area (by location)
Derry City and Strabane
Time to decision
443 weeks
REPD reference
4264

Who decides

ApplicationsDerry City and StrabaneUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused0 of 212%
Onshore wind refused10 of 4345%
Battery storage refused0 of 416%
Median time from submission to decision103.3 weeks17.0 weeks
Appeals lodged / allowed4 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Townlands of Carrickatanewind farm20.7operational1.5
Power Generation in Development in Claudybattery storage75application submitted4.2
Slieve Kirkwind farm27.6operational6.3
Slieve Kirk Extwind farm11.5permission expired6.3
Barr Cregg Wind Farmwind farm12.6approved, not built8.2
Curryfree Wind Farmwind farm15operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8838, -7.2136).