Slieve Kirk (formerly Altahullion Phase III & Glenconway 2) (27.6 MW wind farm)

Slieve Kirk (formerly Altahullion Phase III & Glenconway 2) is a 27.6 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 November 2013; the record was last updated on 12 December 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27.6 MWwind farm
operationalstatus in REPD
12 December 2013record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
11 January 2007Application submitted
26 September 2010Planning permission granted
1 October 2012Construction started
7 November 2013Operational

Project details

Technology
wind farm
Capacity
27.6 MW
Status (REPD)
operational
Record last updated
12 December 2013
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Causeway Coast and Glens
Planning application reference
B/2007/0006/F
Turbines
12
Address (REPD)
Altahullion Phase III Wind Farm in the townlands of Drum, Glenconway and Ballymoney, near Dungiven
Council area (by location)
Causeway Coast and Glens
Time to decision
193 weeks
REPD reference
3955

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Slieve Kirk (formerly Glenconway)wind farm18.4operational0.7
Altahullionwind farm26operational0.9
Altahullion Phase IIwind farm11.7operational2.2
Farklandwind farm51application withdrawn3.5
62 Muldonagh Road, Claudywind turbine8.8application submitted4.8
Monnaboy Wind Farm Ext.wind farm6application withdrawn5.2
Monnaboy Wind Farmwind farm12operational6.4
Ballyhanedin Wind Farmwind farm24approved, not built7.4
Barr Cregg Wind Farmwind farm12.6approved, not built7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9705, -7.0348).