Farkland (51 MW wind farm)

Farkland is a 51 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 11 November 2010; the record was last updated on 29 March 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

51 MWwind farm
application withdrawnstatus in REPD
29 March 2011record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
12 December 2007Application submitted
11 November 2010Application withdrawn

Project details

Technology
wind farm
Capacity
51 MW
Status (REPD)
application withdrawn
Record last updated
29 March 2011
Operator or applicant
Ted Walsh & Associates
Planning authority
Causeway Coast and Glens
Planning application reference
B/2007/0562/F
Turbines
17
Address (REPD)
on the south western slopes of Altahullion Hill, 8km from Claudy and south east of Dungiven.
Council area (by location)
Causeway Coast and Glens
REPD reference
2717

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
62 Muldonagh Road, Claudywind turbine8.8application submitted1.9
Altahullionwind farm26operational2.7
Slieve Kirk (formerly Altahullion Phase III & Glenconway 2)wind farm27.6operational3.5
Ballyhanedin Wind Farmwind farm24approved, not built3.9
Slieve Kirk (formerly Glenconway)wind farm18.4operational4.2
Altahullion Phase IIwind farm11.7operational4.4
Monnaboy Wind Farm Ext.wind farm6application withdrawn6.5
Barr Cregg Wind Farmwind farm12.6approved, not built6.6
Monnaboy Wind Farmwind farm12operational7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9391, -7.0426).