Energy Projects Near You

Carneatly (9.2 MW wind farm)

Carneatly is a 9.2 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 7 June 2018; the record was last updated on 3 July 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
application withdrawnstatus in REPD
3 July 2018record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
12 April 2011Application submitted
7 June 2018Application withdrawn

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
application withdrawn
Record last updated
3 July 2018
Operator or applicant
North Power Ltd
Planning authority
Causeway Coast and Glens
Planning application reference
E/2011/0088/F
Turbines
4
Address (REPD)
Ballycastle, Co Antrim
Council area (by location)
Causeway Coast and Glens
REPD reference
4185

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Armoy Wind Farmwind farm19.8refused on appeal8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1934, -6.2959).