Corkey Windfarm (repowering) (20 MW)

Corkey Windfarm (repowering) is a 20 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 March 2022, not yet built; the record was last updated on 9 March 2022. REPD also records that the planning permission expired on 2 March 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWwind farm
approved, not builtmay be out of datestatus in REPD
9 March 2022record last updated
Causeway Coast and Glenscouncil area

REPD also records that the planning permission expired on 2 March 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
9 July 2019Application submitted
2 March 2022Planning permission granted
2 March 2025Permission expired

Project details

Technology
wind farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
9 March 2022
Operator or applicant
ScottishPower Renewables
Planning authority
Causeway Coast and Glens
Planning application reference
LA01/2019/0772/F
Turbines
5
Turbine height
137 m
Address (REPD)
Corkey Windfarm, Corkey Road, Approx 19km North of Ballymena, Ballymena,
Council area (by location)
Causeway Coast and Glens
Time to decision
138 weeks
REPD reference
7543

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Corkey Wind Farmwind farm5operational2.0
Gruig Wind Farmwind farm25operational2.1
Carnbuck Wind Farmwind farm50.4application submitted4.0
Altaveedan Wind Farmwind farm17.9operational5.8
Armoy Wind Farmwind farm19.8refused on appeal9.5
Glenbuckwind farm6.9operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0326, -6.2629).