Dungiven (24 MW wind farm)

Dungiven is a 24 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 31 July 2025, not yet built; the record was last updated on 7 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWwind farm
approved, not builtstatus in REPD
7 November 2025record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
2 August 2019Application submitted
5 December 2023Refused by the planning authority
31 July 2025Planning permission granted
31 July 2025Appeal allowed
31 July 2030Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
24 MW
Status (REPD)
approved, not built
Record last updated
7 November 2025
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Causeway Coast and Glens
Planning application reference
LA01/2019/0922/F
Appeal reference
2023/A0099
Turbines
6
Turbine height
150 m
Address (REPD)
Lands Opp entrance to, 59 Magheramore Road, Dungiven, Derry, Co Londonderry
Council area (by location)
Causeway Coast and Glens
Time to decision
313 weeks
REPD reference
7491

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brockaghboy Wind Farm - extensionwind farm10operational4.3
Ballyhanedin Wind Farmwind farm24approved, not built7.1
Brishey Wind Farmwind farm28.8application submitted7.1
Evishagaran Wind Farmwind farm46.8approved, not built7.2
Smulgedonwind farm16.1abandoned8.4
Farklandwind farm51application withdrawn8.7
Altahullion Phase IIwind farm11.7operational9.7
62 Muldonagh Road, Claudywind turbine8.8application submitted9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8911, -6.9343).