Energy Projects Near You

Cloonty Wind Farm (12 MW)

Cloonty Wind Farm is a 12 MW wind farm project in Causeway Coast and Glens, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 August 2016; the record was last updated on 3 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
operationalstatus in REPD
3 January 2017record last updated
Causeway Coast and Glenscouncil area

Planning timeline

DateStage
8 June 2009Application submitted
27 March 2013Planning permission granted
15 October 2015Construction started
15 August 2016Operational

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
3 January 2017
Operator or applicant
Gaelectric Developments/ CGN Europe Energy
Planning authority
Causeway Coast and Glens
Planning application reference
D/2009/0142/F
Turbines
4
Address (REPD)
122 Castlecat Road Derry Keighan, Cloonty Townland, Ballymoney, Co Antrim. BT53 8AP
Council area (by location)
Causeway Coast and Glens
Time to decision
198 weeks
REPD reference
4143

Who decides

ApplicationsCauseway Coast and GlensUK
Decided applications (solar, wind, battery)4710,236
Refused6 (13%)19%
Solar refused0 of 412%
Onshore wind refused6 of 4145%
Battery storage refused0 of 216%
Median time from submission to decision103.0 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Armoy Wind Farmwind farm19.8refused on appeal5.8
Altaveedan Wind Farmwind farm17.9operational9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1185, -6.3958).