Energy Projects Near You

Renewable energy projects in Newry, Mourne and Down

14 solar, wind or battery projects of 150 kW or more are located in Newry, Mourne and Down (REPD, July 2026 extract): 3 pending, 7 approved but not running, 1 operational and 1 refused.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14projects in the council area
3awaiting a decision
7approved, not running
1operational

How Newry, Mourne and Down decides

Newry, Mourne and Down has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Projects in Newry, Mourne and Down

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Gruggandoo Wind Farmwind farmwind farm39.6application submitted may be out of dateupdated May 2015Mar 2015—May 2015
Tullyneilwind farmwind farm13.8application withdrawnupdated Sep 2019May 2013—Sep 2019
Tullynaskeagh Solar Farmsolar farmsolar farm5.1abandonedupdated Sep 2017Aug 2013granted Jan 2014Sep 2017
Solar PV Energy Development in Newrysolar farmsolar farm2approved, not builtupdated May 2026Apr 2024granted May 2026May 2026
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Drumbanagher Wall Road, Poyntzpasswind turbinewind turbine0.5application submitted may be out of dateupdated Dec 2023Nov 2023—Dec 2023
Greenhall Highwaywind turbinewind turbine0.3approved, not built may be out of dateupdated Feb 2021Jul 2019granted Feb 2021Feb 2021
Newry Roadwind turbinewind turbine0.3approved, not builtupdated Apr 2021Aug 2020granted Dec 2021Apr 2021
Dundrinne Roadwind turbinewind turbine0.2operationalupdated Mar 2022Jul 2019granted Oct 2019Mar 2022
Aghincurk Roadwind turbinewind turbine—approved, not built may be out of dateupdated Feb 2021Nov 2020granted Jul 2021Feb 2021
Crabtree Roadbattery storagebattery storage—approved, not builtupdated Sep 2021Jun 2021granted Mar 2022Sep 2021
Wind Turbine Development in Crossgarwind turbinewind turbine—application submitted may be out of dateupdated Dec 2023Oct 2023—Dec 2023
Wind Turbine Development in Downpatrickwind turbinewind turbine—approved, not builtupdated Nov 2025Feb 2024granted Oct 2025Nov 2025
Wind Turbine Development in Ballywardwind farmwind farm—refusedupdated Jun 2026Jun 2025refused May 2026Jun 2026
Turbine Development in Ballynahinchwind farmwind farm—approved, not builtupdated Feb 2026Aug 2023granted Jan 2026Feb 2026

Postcode districts in Newry, Mourne and Down

DistrictProjects within 10 kmPendingApprovedOperational
BT244130
BT301000
BT313011
BT332011
BT341100
BT352020

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Newry, Mourne and Down by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.