Energy Projects Near You

Solar, wind and battery projects near Newry (BT34)

1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of BT34 (Newry, Mourne and Down): 1 is waiting for a planning decision. The largest live scheme is Gruggandoo Wind Farm (39.6 MW wind farm, application submitted on 31 March 2015, no decision recorded; REPD status may be out of date), 3.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1projects within 10 km
1awaiting a decision
0approved, not running
0operational

Projects within 10 km of BT34

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Gruggandoo Wind Farmwind farmwind farm39.6application submitted may be out of dateupdated May 2015Mar 2015—May 2015Newry, Mourne and Down3.1

Distance from the average position of the BT34 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm1100039.6

MW in pipeline: pending, approved and under-construction capacity.

How Newry, Mourne and Down decides solar, wind and battery applications

Newry, Mourne and Down has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Newry, Mourne and Down

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT34, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.