Energy Projects Near You

Solar, wind and battery projects near Portadown (BT63)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT63 (Armagh City, Banbridge and Craigavon): 5 are waiting for a planning decision, 3 approved but not yet running, 2 operational. The largest live scheme is Portadown Road (50 MW battery storage, under construction since 15 January 2020), 4.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
5awaiting a decision
3approved, not running
2operational

Projects within 10 km of BT63

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Gilford Roadrooftop solarrooftop solar1.3operationalupdated Mar 2015Nov 2013granted Jan 2014Mar 2015Armagh City, Banbridge and Craigavon1.5
Portadown Roadbattery storagebattery storage50under constructionupdated Jun 2020Jun 2018—Jun 2020Armagh City, Banbridge and Craigavon4.9
Laurelhillsolar farmsolar farm8.5operationalupdated May 2018Jun 2015granted May 2016May 2018Armagh City, Banbridge and Craigavon8.4
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lowtown Road, Waringstownwind turbinewind turbine0.8application submitted may be out of dateupdated May 2026Nov 2023—May 2026Armagh City, Banbridge and Craigavon4.9
Moy Roadwind turbinewind turbine0.3application submitted may be out of dateupdated Dec 2019Nov 2019—Dec 2019Armagh City, Banbridge and Craigavon7.1
Boconnell Lane, Lurganwind turbinewind turbine—application withdrawnupdated Aug 2025Feb 2025—Aug 2025Armagh City, Banbridge and Craigavon7.6
Tullyrain Roadwind turbinewind turbine0.3approved, not builtupdated Jan 2026Sep 2019granted Dec 2025Jan 2026Armagh City, Banbridge and Craigavon7.8
Huntly Roadwind turbinewind turbine0.5approved, not built may be out of dateupdated Sep 2020Dec 2018granted Sep 2020Sep 2020Armagh City, Banbridge and Craigavon8.0
Power Generation Development in Tandrageewind turbinewind turbine0.8application submittedupdated Aug 2025Feb 2025—Aug 2025Armagh City, Banbridge and Craigavon8.8
Aghory Roadwind turbinewind turbine0.9application submitted may be out of dateupdated Jun 2019Apr 2019—Jun 2019Armagh City, Banbridge and Craigavon9.2
Wind Turbine Development in Donaghcloneywind turbinewind turbine0.6application submittedupdated Nov 2024Aug 2024—Nov 2024Armagh City, Banbridge and Craigavon9.4

Distance from the average position of the BT63 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100100
Rooftop solar100100
Wind turbine852004.3
Battery storage1010050

MW in pipeline: pending, approved and under-construction capacity.

How Armagh City, Banbridge and Craigavon decides solar, wind and battery applications

ApplicationsArmagh City, Banbridge and CraigavonUK
Decided applications (solar, wind, battery)1710,236
Refused2 (12%)19%
Solar refused0 of 412%
Onshore wind refused2 of 1345%
Median time from submission to decision135.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

All projects in Armagh City, Banbridge and Craigavon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT63, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.