Energy Projects Near You

Solar, wind and battery projects near Banbridge (BT32)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT32 (Armagh City, Banbridge and Craigavon): 3 are waiting for a planning decision, 4 approved but not yet running, 1 operational. The largest live scheme is Solar PV Energy Development in Newry (2 MW solar farm, approved on 14 May 2026, not yet built), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
3awaiting a decision
4approved, not running
1operational

Projects within 10 km of BT32

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Laurelhillsolar farmsolar farm8.5operationalupdated May 2018Jun 2015granted May 2016May 2018Armagh City, Banbridge and Craigavon7.5
Old Barrwind farmwind farm20application withdrawnupdated Oct 2013Nov 2004—Oct 2013Armagh City, Banbridge and Craigavon9.0
Solar PV Energy Development in Newrysolar farmsolar farm2approved, not builtupdated May 2026Apr 2024granted May 2026May 2026Newry, Mourne and Down9.9
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Huntly Roadwind turbinewind turbine0.5approved, not built may be out of dateupdated Sep 2020Dec 2018granted Sep 2020Sep 2020Armagh City, Banbridge and Craigavon4.6
Tullyrain Roadwind turbinewind turbine0.3approved, not builtupdated Jan 2026Sep 2019granted Dec 2025Jan 2026Armagh City, Banbridge and Craigavon5.9
Garvaghy Roadwind turbinewind turbine0.3application submitted may be out of dateupdated Sep 2021Jun 2020—Sep 2021Armagh City, Banbridge and Craigavon7.1
Garvaghy Road Replacement Turbinewind turbinewind turbine—approved, not builtupdated Jul 2024Feb 2021granted Jun 2024Jul 2024Armagh City, Banbridge and Craigavon8.0
Lowtown Road, Waringstownwind turbinewind turbine0.8application submitted may be out of dateupdated May 2026Nov 2023—May 2026Armagh City, Banbridge and Craigavon8.7
Wind Turbine Development in Donaghcloneywind turbinewind turbine0.6application submittedupdated Nov 2024Aug 2024—Nov 2024Armagh City, Banbridge and Craigavon9.7

Distance from the average position of the BT32 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201102
Wind farm100000
Wind turbine633002.6

MW in pipeline: pending, approved and under-construction capacity.

How Armagh City, Banbridge and Craigavon decides solar, wind and battery applications

ApplicationsArmagh City, Banbridge and CraigavonUK
Decided applications (solar, wind, battery)1710,236
Refused2 (12%)19%
Solar refused0 of 412%
Onshore wind refused2 of 1345%
Median time from submission to decision135.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

All projects in Armagh City, Banbridge and Craigavon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT32, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.