Energy Projects Near You

Solar, wind and battery projects near Dromore (BT25)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT25 (Armagh City, Banbridge and Craigavon): 5 are waiting for a planning decision, 3 approved but not yet running, 1 operational. The largest live scheme is 8 Church Road, Dromara (0.8 MW wind turbine, approved on 8 June 2026, not yet built), 3.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
5awaiting a decision
3approved, not running
1operational

Projects within 10 km of BT25

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Old Barrwind farmwind farm20application withdrawnupdated Oct 2013Nov 2004—Oct 2013Armagh City, Banbridge and Craigavon1.9
Slieve Croobwind turbinewind turbine2.3refusedupdated Apr 2012Dec 2007refused Feb 2012Apr 2012Armagh City, Banbridge and Craigavon4.5
Laurelhillsolar farmsolar farm8.5operationalupdated May 2018Jun 2015granted May 2016May 2018Armagh City, Banbridge and Craigavon9.7
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lagangreen Roadwind turbinewind turbine0.2approved, not builtupdated Feb 2024Jun 2019granted Feb 2024Feb 2024Armagh City, Banbridge and Craigavon2.2
Power Generation Development in Dromorewind turbinewind turbine—application submittedupdated Sep 2025Sep 2025—Sep 2025Armagh City, Banbridge and Craigavon2.9
Garvaghy Road Replacement Turbinewind turbinewind turbine—approved, not builtupdated Jul 2024Feb 2021granted Jun 2024Jul 2024Armagh City, Banbridge and Craigavon3.5
8 Church Road, Dromarawind turbinewind turbine0.8approved, not builtupdated Jul 2026Apr 2023granted Jun 2026Jul 2026Armagh City, Banbridge and Craigavon3.8
Garvaghy Roadwind turbinewind turbine0.3application submitted may be out of dateupdated Sep 2021Jun 2020—Sep 2021Armagh City, Banbridge and Craigavon4.4
Wind Turbine Development in Dromorewind turbinewind turbine—application submittedupdated Nov 2024Sep 2024—Nov 2024Armagh City, Banbridge and Craigavon5.7
Rathfriland Roadwind turbinewind turbine0.3application submitted may be out of dateupdated Sep 2019Jul 2019—Sep 2019Armagh City, Banbridge and Craigavon6.4
Wind Turbine Development in Donaghcloneywind turbinewind turbine0.6application submittedupdated Nov 2024Aug 2024—Nov 2024Armagh City, Banbridge and Craigavon9.3

Distance from the average position of the BT25 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100100
Wind farm100000
Wind turbine953012.2

MW in pipeline: pending, approved and under-construction capacity.

How Armagh City, Banbridge and Craigavon decides solar, wind and battery applications

ApplicationsArmagh City, Banbridge and CraigavonUK
Decided applications (solar, wind, battery)1710,236
Refused2 (12%)19%
Solar refused0 of 412%
Onshore wind refused2 of 1345%
Median time from submission to decision135.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

All projects in Armagh City, Banbridge and Craigavon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT25, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.