Tullyneil (13.8 MW wind farm)

Tullyneil is a 13.8 MW wind farm project in Newry, Mourne and Down, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 23 August 2019; the record was last updated on 27 September 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.8 MWwind farm
application withdrawnstatus in REPD
27 September 2019record last updated
Newry, Mourne and Downcouncil area

Planning timeline

DateStage
3 May 2013Application submitted
23 August 2019Application withdrawn

Project details

Technology
wind farm
Capacity
13.8 MW
Status (REPD)
application withdrawn
Record last updated
27 September 2019
Operator or applicant
Gaelectric
Planning authority
Armagh City, Banbridge and Craigavon
Planning application reference
O/2013/0190/F
Turbines
6
Turbine height
85 m
Address (REPD)
Land 80m south of junction of Chalybeate Road and Keady Road (A29) in the townland of Dangary and Tullyneill Newtownhamilton Co Armagh
Council area (by location)
Newry, Mourne and Down
REPD reference
6188

Who decides

ApplicationsArmagh City, Banbridge and CraigavonUK
Decided applications (solar, wind, battery)1710,236
Refused2 (12%)19%
Solar refused0 of 412%
Onshore wind refused2 of 1345%
Median time from submission to decision135.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.2094, -6.6154).