Energy Projects Near You

Belford Burn Windfarm (22.5 MW)

Belford Burn Windfarm is a 22.5 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 8 October 2014; the record was last updated on 6 November 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22.5 MWwind farm
refusedstatus in REPD
6 November 2014record last updated
Northumberlandcouncil area

Planning timeline

DateStage
9 July 2013Application submitted
8 October 2014Refused by the planning authority

Project details

Technology
wind farm
Capacity
22.5 MW
Status (REPD)
refused
Record last updated
6 November 2014
Operator or applicant
Energiekontor UK
Planning authority
Northumberland
Planning application reference
13/02050/RENEIA
Turbines
9
Address (REPD)
Sionside Farm, on land adjacent to the Middleton Burn site, just north of Belford Moor. , Northumberland
Council area (by location)
Northumberland
Time to decision
65 weeks
REPD reference
4195

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.595, -1.8767).