Bourne Park (Solar) (5 MW)

Bourne Park (Solar) is a 5 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 March 2015; the record was last updated on 28 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
28 May 2015record last updated
Dorsetcouncil area

Planning timeline

DateStage
9 August 2013Application submitted
30 October 2013Planning permission granted
1 January 2015Construction started
19 March 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
28 May 2015
Operator or applicant
Sovereign Energy Partners LLP
Planning authority
Dorset
Planning application reference
1/D/13/001116
Site area
18.7 ha
Address (REPD)
Hanford Plc, Bourne Park, Piddlehinton, Dorchester
Council area (by location)
Dorset
Time to decision
12 weeks
REPD reference
2361

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Slyer's Lanewind farm18refused4.6
Yellowham solar parksolar farm20refused on appeal4.8
West Dorset Wind Farmwind farm12.5application withdrawn7.4
Crossways Pit Solar Farmsolar farm5operational10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7779, -2.3943).