Energy Projects Near You

Carsington Pasture (8 MW wind farm)

Carsington Pasture is an 8 MW wind farm project in Derbyshire Dales, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 5 February 2014; the record was last updated on 16 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWwind farm
operationalstatus in REPD
16 September 2014record last updated
Derbyshire Dalescouncil area

Planning timeline

DateStage
29 January 2007Application submitted
20 July 2007Refused by the planning authority
17 September 2008Planning permission granted
17 September 2008Appeal allowed
15 May 2012Construction started
5 February 2014Operational

Project details

Technology
wind farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
16 September 2014
Operator or applicant
Carsington Wind Energy Limited
Planning authority
Derbyshire Dales
Planning application reference
07/00083/FUL
Appeal reference
07/00015/INQUIR
Turbines
4
Address (REPD)
Carsington Pasture, Derbyshire Dales
Council area (by location)
Derbyshire Dales
Time to decision
85 weeks
REPD reference
4665

Who decides

ApplicationsDerbyshire DalesUK
Decided applications (solar, wind, battery)2210,236
Refused5 (23%)19%
Solar refused2 of 1712%
Onshore wind refused3 of 545%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ryder Point Quarry Wind Turbineswind farm5operational1.1
Griffe Grange Wind Farmwind farm12.3refused on appeal1.2
Smith Hall Farm Solar Parksolar farm5operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0845, -1.6336).