Griffe Grange Wind Farm (12.3 MW)

Griffe Grange Wind Farm is a 12.3 MW wind farm project in Derbyshire Dales, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 6 December 2016; the record was last updated on 23 December 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.3 MWwind farm
refused on appealstatus in REPD
23 December 2016record last updated
Derbyshire Dalescouncil area

Planning timeline

DateStage
9 April 2014Application submitted
9 March 2015Refused by the planning authority
30 September 2015Appeal lodged
6 December 2016Appeal refused

Project details

Technology
wind farm
Capacity
12.3 MW
Status (REPD)
refused on appeal
Record last updated
23 December 2016
Operator or applicant
Njord Energy Ltd
Planning authority
Derbyshire Dales
Planning application reference
14/00224/FUL
Appeal reference
APP/P1045/W/15/3130874
Turbines
5
Address (REPD)
near the Valero oil refinery south of Milford Haven
Council area (by location)
Derbyshire Dales
Time to decision
48 weeks
REPD reference
4276

Who decides

ApplicationsDerbyshire DalesUK
Decided applications (solar, wind, battery)2210,236
Refused5 (23%)19%
Solar refused2 of 1712%
Onshore wind refused3 of 545%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carsington Pasturewind farm8operational1.2
Ryder Point Quarry Wind Turbineswind farm5operational1.7
Smith Hall Farm Solar Parksolar farm5operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0925, -1.6465).