Cenos offshore wind farm
Cenos Offshore Wind Farm is a 1,350 MW offshore wind farm with 95 turbines in Scottish waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 31 January 2025, no decision recorded; the record was last updated on 7 April 2025. REPD gives no grid reference for it. As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.
Consent timeline
| Date | Stage |
|---|---|
| 31 January 2025 | Application submitted |
Project details
- Technology
- offshore wind farm
- Capacity
- 1,350 MW
- Turbines
- 95
- Turbine capacity
- 14 MW
- Turbine height
- 320 m
- Status (REPD)
- application submitted
- Record last updated
- 7 April 2025
- Operator or applicant
- Flotation Energy
- Consenting authority (REPD)
- Marine Scotland
- Application reference
- 25995
- REPD reference
- 13528
Who decides
As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.
All offshore wind farms in UK waters
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions.