Chapel Lane (49.4 MW battery storage)

Chapel Lane is a 49.4 MW battery storage project in Walsall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 January 2025, not yet built; the record was last updated on 21 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.4 MWbattery storage
approved, not builtstatus in REPD
21 January 2025record last updated
Walsallcouncil area

Planning timeline

DateStage
5 October 2023Application submitted
3 July 2024Appeal lodged
13 January 2025Planning permission granted
13 January 2025Appeal allowed
13 January 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.4 MW
Status (REPD)
approved, not built
Record last updated
21 January 2025
Operator or applicant
Anesco Limited
Planning authority
Walsall
Planning application reference
23/1286
Appeal reference
APP/V4630/W/24/3347424
Address (REPD)
Adj The Duckery, Chapel Lane, Great Barr, Walsall
Council area (by location)
Walsall
Time to decision
67 weeks
Name in REPD
Chapel Lane - Battery Energy Storage System
REPD reference
15308

Earlier applications for this site

ApplicationMWSubmittedOutcome
Chapel Lane 21/172049.46 December 2021refused 13 December 2022

Who decides

ApplicationsWalsallUK
Decided applications (solar, wind, battery)2110,236
Refused5 (24%)19%
Solar refused2 of 1612%
Battery storage refused3 of 516%
Median time from submission to decision7.3 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bustleholme Substationbattery storage49.9operational2.4
Bloxwich Batterybattery storage41operational6.5
Midland Quarry Products, Smith Roadbattery storage10approved, not built7.0
Golds Hillbattery storage57operational7.7
Maybrook Road Battery facilitybattery storage13.1approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5625, -1.9251).