Chase Farm (18.4 MW wind farm)
Chase Farm is an 18.4 MW wind farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 16 December 2010; the record was last updated on 15 May 2011.
18.4 MWwind farm
refused on appealstatus in REPD
15 May 2011record last updated
East Lindseycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 17 July 2009 | Application submitted |
| 16 December 2010 | Refused by the planning authority |
| 16 December 2010 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 18.4 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 15 May 2011
- Operator or applicant
- Enertrag UK Limited
- Planning authority
- East Lindsey
- Planning application reference
- S/011/01270/09
- Appeal reference
- APP/D2510/A/10/2121089
- Turbines
- 8
- Address (REPD)
- Bardney Road, Baumber, Horncastle, Lincs
- Council area (by location)
- East Lindsey
- Time to decision
- 74 weeks
- REPD reference
- 2689
Who decides
| Applications | East Lindsey | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 11 (22%) | 19% |
| Solar refused | 0 of 30 | 12% |
| Onshore wind refused | 11 of 15 | 45% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 17.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Hatton Solar Farm | solar farm | 49.9 | approved, not built | 3.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2466, -0.1797).