Energy Projects Near You

Chase Farm (18.4 MW wind farm)

Chase Farm is an 18.4 MW wind farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 16 December 2010; the record was last updated on 15 May 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.4 MWwind farm
refused on appealstatus in REPD
15 May 2011record last updated
East Lindseycouncil area

Planning timeline

DateStage
17 July 2009Application submitted
16 December 2010Refused by the planning authority
16 December 2010Appeal refused

Project details

Technology
wind farm
Capacity
18.4 MW
Status (REPD)
refused on appeal
Record last updated
15 May 2011
Operator or applicant
Enertrag UK Limited
Planning authority
East Lindsey
Planning application reference
S/011/01270/09
Appeal reference
APP/D2510/A/10/2121089
Turbines
8
Address (REPD)
Bardney Road, Baumber, Horncastle, Lincs
Council area (by location)
East Lindsey
Time to decision
74 weeks
REPD reference
2689

Who decides

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hatton Solar Farmsolar farm49.9approved, not built3.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2466, -0.1797).