Hatton Solar Farm (49.9 MW)

Hatton Solar Farm is a 49.9 MW solar farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 December 2025, not yet built; the record was last updated on 26 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
26 January 2026record last updated
East Lindseycouncil area

Planning timeline

DateStage
24 June 2022Application submitted
30 April 2025Appeal lodged
12 December 2025Planning permission granted
12 December 2025Appeal allowed
12 December 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
26 January 2026
Operator or applicant
Push Energy
Planning authority
East Lindsey
Planning application reference
S/079/01078/22
Appeal reference
AP/02008/25/REF
Site area
73.4 ha
Address (REPD)
Adj Sotby Woods, Sturton Road, Market Rasen
Council area (by location)
East Lindsey
Time to decision
181 weeks
REPD reference
11460

Who decides

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chase Farmwind farm18.4refused on appeal3.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2749, -0.2137).