Chediston Hall - 40MW Solar Panels (40 MW)

Chediston Hall - 40MW Solar Panels is a 40 MW solar farm project in East Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 13 June 2025, no decision recorded; the record was last updated on 11 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
application submittedstatus in REPD
11 August 2025record last updated
East Suffolkcouncil area

Planning timeline

DateStage
13 June 2025Application submitted

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
application submitted
Record last updated
11 August 2025
Operator or applicant
Sky UK Development Limited
Planning authority
East Suffolk
Planning application reference
DC/25/2021/FUL
Site area
56.5 ha
Address (REPD)
Chediston Hall, Halesworth
Council area (by location)
East Suffolk
REPD reference
19230

Who decides

ApplicationsEast SuffolkUK
Decided applications (solar, wind, battery)5510,236
Refused10 (18%)19%
Solar refused3 of 3812%
Onshore wind refused5 of 845%
Battery storage refused2 of 916%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chediston Hall Solar Parksolar farm12.3operational0.8
Wissett Solar Farm, Wissett Battery Storage (Apple Tree)battery storage10approved, not built0.9
Solar Photovoltaic (PV) Farm (Apple Tree)solar farm27approved, not built0.9
Norwich Road Industrial Estatebattery storage50under construction2.3
Hill Farmsolar farm15.9abandoned2.7
Holton Airfieldsolar farm11operational3.5
Upper Holton Wind Farmwind farm11.5operational4.2
Bernard Matthews Wind Farmwind farm11.5application withdrawn4.2
Redisham Hall Farm, School Roadsolar farm42application submitted9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3458, 1.48).